FIDIC Engineer for the modernization of the existing railway Line Durres – Tirana and the construction of the new railway connection to Tirana International Airport, Albania

Technical Details

The project comprises the rehabilitation of the existing single-track railway line between the Port of Durres and the capital, Tirana, with a total length of 34.2 km, as well as the construction of a new 5.6 km single-track branch line connecting to Tirana International Airport. The overall project length amounts to 39.8 km. 

Key infrastructure components include 8 new railway bridges, one tunnel, retaining walls and culverts, 21 level crossings, and 5 pedestrian underpasses at stations. The scope covers both civil works and signalling & telecommunications systems and is implemented under the FIDIC 1999 Conditions of Contract, Yellow Book.

In addition, the project includes the development of 8 stations and stops along the line. These works are being carried out under the FIDIC 1999 Conditions of Contract (Red Book) and involve the construction of new station buildings, platforms, and surrounding areas, all designed to ensure full accessibility.

Design and construction comply with the Technical Specifications for Interoperability (TSI) for the European railway network. 

Multi-storey building under construction with scaffolding, brick walls, and stacked materials
Railway tracks through a construction site with workers and steel platform canopies
Railway turnout and trackwork under construction with signal masts and a maintenance excavator
Railway track junction with switch points and signal masts near a town

Services Provided

The scope of services covers the full role of the FIDIC Engineer, acting on behalf of the Client during project implementation by the Contractors (FIDIC 1999 Yellow & Red Book).

Services include, inter alia:

  • Design review and approval
  • Construction supervision and site management
  • Quality assurance and project monitoring
  • Contract administration
  • Variations and claims management
  • Support during testing, commissioning, and project handover
39.8 kmOverall Project Length
34.2 kmRehabilitation Section
5.6 kmNew Branch Line
8Railway Bridges
1Tunnels
21Level Crossings
5Pedestrian Underpasses
8Stations and Stops
2Traction Power Substations

Technical Specifications

Design speed 100–120 km/h
Standard gauge 1,435 mm
Track System Continuously welded rails
Signalling ETCS Level 1, with provision for future upgrade to ERTMS/ETCS Level 2
Safety integrity level SIL4 in accordance with CENELEC EN 50129
Transmission System NGSDH/IP
Electrification Provision for electrification, including two new traction power substations